Project to repair canal walls and replace bridges at Ala Moana Regional Park
Wider pedestrian bridges near Queen and Pi'ikoi streets to align with existing Ala Moana Blvd. crosswalks
HONOLULU – A Capital Improvement Project to repair the damaged drainage canal walls and replace two pedestrian bridges over the drainage canal at Ala Moana Regional Park began this week.
Roughly 900-feet of the drainage canal wall between the 'Ewa-side Japanese Pond and tennis courts will be repaired or replaced, including the portion that collapsed in 2016. The fallen sections of the existing walls will be replaced with a precast reinforced concrete wall, and the repaired wall sections will be reconstructed with concrete rubble masonry.
The pedestrian bridges over the drainage canal near Queen Street and Pi'ikoi streets will be removed and replaced with wider bridges that align with the crosswalks on Ala Moana Boulevard. The existing bridges measure about 10' wide and the new bridge near Queen Street will be twice as wide, while the new bridge near Pi'ikoi Street will be triple the width. Both bridges will additionally have decorative railings and abutments that reflect the art-deco architectural features prevalent in this historic park.
"This pedestrian bridge will provide central and much needed pedestrian access to Ala Moana Regional Park, the most heavily used park in the state, and sometimes called the 'People's Park," said Mayor Kirk Caldwell. "Also to be repaired are the collapsed coral block canal wall built at the inception of the park in the 1930's that collapsed into the canal a couple years ago. These continued improvements are all part of an ongoing effort to take care of an irreplaceable natural resource for our residents that has been neglected for decades, and allowed to degrade. The park has received much care and support over the last eight years and its incredible beauty is shining through once again."
Exceptional Trees in the project area will be protected, however three trees along the makai-end of the canal wall will be relocated and one will be removed to reduce damage to the canal walls. The project will additionally result in the planting of 22 new palm trees, primarily near the bridge entries.
Due to the delivery of large precast materials for this project, vehicular traffic along the makai lanes of Ala Moana Boulevard will be intermittently impacted during the project, and will require partial closure. Additionally, pedestrian access at the construction site and on the two bridges being replaced will be restricted during the project. We ask the public to please be cautious in these areas during the project. The pedestrian bridges near Kamake'e Street and the Hawaiian Pond are expected to remain open and accessible during construction.
The approximately $4.62 million contract for the construction was awarded to Kaikor Corporation.
The project is scheduled to be completed by Winter 2021.
—PAU—
Tuesday, Nov. 24, 2020
'Āina Moana Parking Lot reopened to the public
Majority of reconstruction work completed, some maintenance and work remain
HONOLULU – The 'Āina Moana (Magic Island) Parking Lot was reopened to vehicular traffic today following the completion of a majority of the reconstruction project.
The 470-stall parking lot was completely repaved and restriped, with the installation of new gates, benches, and a drop-off zone. Additional improvements were made to the tree planting spaces, irrigation, and curbing, with a one-for-one replacement of unhealthy trees accompanying the planting of new trees. These efforts were made to help these Monkeypod, Geometry, and Hau trees to thrive and provide a sufficient canopy to cool the area beneath them.
"Throughout our administration we have given much needed care to Ala Moana, the People's Park, after it had been neglected for decades" said Mayor Kirk Caldwell. "Now the most popular park in the State can continue to serve our island, and help create many more memories for our local families with improvements to the: roadway, parking, irrigation, beach, bathrooms, showers, exercise equipment, pathways, tree inventory, McCoy Pavilion, staffing, and security. All of this while making this location the first City park to convert completely to LED lights and house the first dedicated sand volleyball courts."
With the addition of dozens of recent tree plantings at 'Āina Moana, over 300 trees have been planted in Ala Moana Regional Park over the last four years. This includes a wide variety of species ranging from Loulu palms to Lonomea, Beach Heliotrope to Shower trees.
While the public may now begin using the highly demanded parking stalls at 'Āina Moana, there remains additional work to be conducted by the project's contractor, Road Builders Corporation, such as landscaping maintenance and restoration.
"With the tumultuous nature of this year, it will be nice to get back to some level of normalcy by reopening roughly half of the parking spots at our most popular park," said Honolulu Department of Parks and Recreation Director Michele Nekota. "We appreciate the patience of the park users while these parking spots received a much-needed makeover. There is still some work to be done, so we appreciate your understanding as the project continues."
—PAU—
October 13, 2020
Hawaiian Pond shoreline improvement project beginning at Ala Moana Regional Park
HONOLULU – A Capital Improvement Project is beginning this week create a more inviting and stable shoreline along the Hawaiian Pond at Ala Moana Regional Park.
Constructed as a flood control basin for storm water drainage, the banks of the Hawaiian Pond located near the park's entrance at Atkinson Drive have become severely eroded. This has created a pond perimeter that is muddy and not frequently used by park goers, as the ponds water levels regularly fluctuate due to tidal conditions and runoff from the mauka streams.
In order to prevent further erosion and sediment run-off, this project will place Flexamat® pre-cast concrete bank stabilization material along the edges of the pond.
The scope of the work also includes: repairs to the central bridge over the pond, construction of a lit walkway connecting the bridge to other mauka pathways, a new seating area along the 'Ewa-end of the pond, replacement of eight trees from the pond's edge to a more stable location mauka of the pond, and protection of Exceptional Trees near the construction zone.
The over $1.96 million contract for this project was awarded to Hawaiian Dredging Construction Company, Inc.
The project is expected to be finished in summer 2021.
—PAU—
April 9, 2020
'Āina Moana parking lot reconstruction beginning April 13
The extensive work is expected to be finished, with the improved parking lot reopened, by end of 2020
'ĀINA MOANA – With City parks closed and essential construction activity continuing amidst the COVID-19 (Coronavirus) pandemic, the City will begin an extensive reconstruction project to revitalize the badly degraded parking lot at 'Āina Moana (Magic Island) on Monday, April 13.
This 470 stall parking lot represents about half of the parking stalls within the People's Park, and is slated for major improvements, including:
- Complete repaving and restriping
- Improvements to tree planters such as: new curbing, irrigation, replacement of damaged trees, and new tree plantings
- Removal of tree roots causing pavement damage
- Construction of a new drop off zone
- Installation of new trash cans, benches, and park road gates
The footprint of the parking lot will remain the same.
The over $2.5 million construction contract for this 'Āina Moana project was awarded to Road Builders Corporation.
These improvements include significant excavation and subterranean work, which will require the closure of the parking lot for the duration of the project. The project is expected to be finished by the end of this year.
At the time of this announcement, all City parks remained closed to the public and park events cancelled to help mitigate the spread of COVID-19 (Coronavirus). When the parks reopen, the following measures will be taken to reduce the impact of this repaving project to the public:
- The pedestrian pathway bordering the parking lot on the Diamond Head-side is anticipated to remain open during the entire length of the project.
- In addition, the People's Open Market held within the parking lot on Monday mornings will be moved to the Canoe Hale Parking Lot between 'Āina Moana and Atkinson Drive.
This project is a continuation of the multi-million dollar effort to revitalize what is normally Hawai'i's most popular and heavily visited park. As part of that effort, the City has completed numerous projects at AMRP over the past couple of years. These projects include:
- Comfort stations and bathhouse renovations
- Planting approximately 220 trees
- LED light improvements throughout the park
- Irrigation upgrades for the entire 119-acre park
- Installation of exercise equipment
- Repaved walking paths and park roadway
- Improvements to McCoy Pavilion
- Creation of the City's first designated off-beach sand volleyball courts
In tangent with these improvements to AMRP, the Mayor Caldwell's Kākou for Parks Program has produced improvements to nearly 200 different parks around the island since 2015.
Parks and Recreation staff continue to work with organizers of popular Ala Moana events, and the general public, during this parking lot reconstruction project and the COVID-19 closures.
UPDATE 4/29/20 DUE TO CONCERNS OVER THE PARKING LOT TREE REPLACEMENTS:
This improvement project is a Honolulu Department of Design and Construction project conducted with coordination from the Honolulu Department of Parks and Recreation, which includes the City's Division of Urban Forestry and its staff of certified arborists. There are various reasons for the replacement of these 26 trees including health of the trees, structural integrity, and survivability. We do not remove trees for no reason. In fact, our goal with this project is to provide a better area for these new trees to thrive, with modified planting spaces and improved irrigation.
Here is a breakdown of the trees that were removed and their replacements:
Trees to be removed: total = 26
(9) Pink Tecoma
(7) Monkeypod Trees
(6) Banyan Trees
(4) False Kamani
Trees to be planted: total = 26
(13) Monkeypod Trees
(13) Hau Trees
All Honolulu Department of Design and Construction projects undergo an extensive environmental impact process, along with allowing opportunities for community input.
Since 2016 over 220 trees have been planted at Ala Moana Regional Park, many of which were recently planted on the makai section of Magic Island. The City is very much dedicated to increasing our tree inventory and shade cover, as expressed in our goals to plant 100,000 trees by 2025 and increase urban canopy cover to 35% by 2035.
—PAU—
Feb. 3, 2020
LED light conversion project beginning at Ala Moana Regional Park
$80,000 in annual savings to result from replacing 570 exterior lights
HONOLULU – Following the successful conversion of over 53,000 street lights to more efficient LED lights (light-emitting diode) in October 2019, the energy saving initiative is coming to the People's Park.
An improvement project to replace the exterior park lights at Ala Moana Regional Park has begun, with the project scheduled to be completed this summer.
This project will upgrade approximately 570 of the existing lights, from high pressure sodium and metal halide lights to LED, located along the park roadways, walkways, parking lots and tennis courts. This will make Ala Moana Regional Park the first City park to have all exterior LED lights.
The new LED lights will use 60% less energy than the previous lights, resulting in an annual saving of $80,000. In effect, the project will pay for itself in just over 15 years.
"The rapid construction of our 53,000 street lights over the past couple of years has incentivized us to take the next phase into our parks, starting with Ala Moana Regional Park, the state's most heavily used park." said Mayor Kirk Caldwell. "As we continue to focus on ways to use energy more efficiently and integrate more sustainable practices across the island, it makes sense for our parks and natural areas to be part of the solution as they are ground zero for experiencing the impacts of the climate crisis. Not only will these lights be more efficient and cost effective, but they are also brighter creating a safer park atmosphere. That has always been one of our administration's top priorities."
The project will be conducted at night, during park closure and non-peak hours, to minimize impact to the public.
The $1.25 million contract for the conversion project was awarded to Pacific Power Electrical Contracting, LLC.
Ala Moana Regional Park, the most popular park in the state, has recently benefitted from several completed improvement projects, including:
- Repaving the Ala Moana Park Drive
- Renovations of park bathhouses and comfort stations (including LED conversions)
- Upgraded irrigation for the entire 119-acre park
- Shower renovations at the base of 'ĀinaMoana (Magic Island)
Other large scale projects expected for the coming year include 'Āina Moana parking lot improvements and repairs to the park ponds.
-PAU-
Thursday, Sept. 5, 2019
Mayor highlights renovation projects at Ala Moana Regional Park
Improvement project for 'Ewa-end bathhouse completed and reopened to the public
HONOLULU – Mayor Kirk Caldwell was joined by city administrators today to highlight a wide variety of improvements to Ala Moana Regional Park, as well as improvements made through his Kākou for Parks program, during a press conference this afternoon.
To view the press conference, which was live-streamed on mayor's Facebook page, please click here.
Most recently renovations were completed to the 'Ewa-side bathhouse at Ala Moana Regional Park, and the facility is now open for public use. This renovation project, similar to the upgrades made to the Diamond Head-side bathhouse last summer, included:
- Replacing the existing roofing and gutter system
- Installing skylights to improve natural lighting
- Adding security measures such as gates and screens
- Exterior painting and repairs
- Retiling and interior cleaning
- Attaching new bathroom fixtures
- Improving ADA accessibility
- Adding a new water fountain
An area on the side of the bathhouse remains closed at this time as an extra month is needed to allow for the proper regrowth of grass.
Security cameras, which were installed and operating prior to this renovation project, have been reinstalled and are now operational.
The $883,000 contract for this project was completed by Starcom Builders Inc.
In addition, the Final Environmental Impact Statement (FEIS) for additional improvement projects at Ala Moana Regional Park is now available online. You can access the FEIS by clicking here. This document will provide the best information about proposed improvement plans to the park. Determination about which projects move forward is made at a different time, and will additionally depend on funding availability and consideration of comments received during the HRS Chapter 343 and HAR Chapter 11-200 Environmental Impact Statement Rules process.
"After decades of neglect this administration is focused on improving the basic infrastructure at Ala Moana and this will be a tremendous benefit to the local residents who visit this treasured park," said Mayor Caldwell. "As we increase density in our urban core to allow the 'country to be more country,' it's critical that we make commonsense improvements to Ala Moana so it remains an inviting place for people of all ages. We all come to Ala Moana for different reasons and these projects are designed to accommodate everyone who have made it the most heavily used park in our state. Much like our Kākou for Parks initiative has made improvements to 160 different parks across O'ahu, we are giving Ala Moana the love it deserves."
Other on-going projects at Ala Moana Regional Park include the repaving of the park road, which is scheduled to be finished this fall, and the installation of a new air conditioning system in the McCoy Pavilion Auditorium, scheduled to be finished this coming winter.
These improvements, and the projects outlined in the FEIS, supplement the goals accomplished by Mayor Caldwell's 9-Point Community Action Plan at Ala Moana Regional Park:
- Hire park staff
- Renovate comfort stations
- Repair ʻĀina Moana (Magic Island) exercise path and exercise amenities
- Irrigate Great Lawn
- Fix rocky beach areas
- Beautify the park
- Build a new playground
- Make the park safer
- Local favorites in the concession
More information about Ala Moana Regional Park can be found by accessing the park's special webpage.
The Mayor's Kākou for Park Program continues to deliver improvements to parks island-wide. From 2015 to the end of last August the program has delivered improvements to 160 different parks, including:
- 114 new and refurbished play apparatus
- 87 renovated comfort stations
- 329 resurfaced play courts
- 81 lined pickleball courts
-PAU-
Monday, July 15, 2019
Ala Moana Park Drive improvement project beginning in August
Most of scheduled work planned during non-peak, park closure hours to minimize impact to public
Mayor Kirk Cadwell was joined by Dept. of Parks and Recreation Deputy Director Jeanne Ishikawa and Dept. of Design and Construction Deputy Director Mark Yonamine to announce the park drive repacing project. Click here to watch the archived live stream of that announcement.
ALA MOANA – In the continuing effort to upgrade the most popular park in the state, the project to improve the main road in Ala Moana Regional Park is scheduled to begin in August, barring unforeseen delays.
The improvements, which call for the repaving, reconstructing, and restriping of the entire stretch of Ala Moana Park Drive, are scheduled to be finished by October. Tree pruning is also planned, along with the installation of new speed bumps and vehicle loop sensors at the park road intersections with street lights.
The parking lot by the canoe hale will be improved, and will also serve as the staging ground for the contractor's equipment. Additional portions of the ʻĀina Moana (Magic Island) parking lot may be used for the staging of equipment. Improvements to this parking lot are anticipated in a separate project.
The work to resurface Ala Moana Park Drive does not include the reorientation of parking stalls.
The $1.04 million contract for the work was awarded to Maui Kupono Builder LLC.
The majority of the scheduled work is being conducted during non-peak park usage hours and regular park closure hours to minimize impact to the public. As a result, the night work schedule is as follows:
- Monday through Thursday 7 p.m. to 5:30 a.m.
- Friday from 12 a.m. (midnight) to 5:30 a.m.
- Sunday from 7 p.m. to 12 a.m. (midnight)
Please not that additional work may be necessary during the daytime, from Mondays through Fridays, 8:30 a.m. to 3:30 p.m.
The above schedule provides several benefits: it minimizes the impact of the work on the public, vehicular traffic, and other park improvement projects, while allowing for more continuous and expedited work.
Park users are advised that "NO PARKING" signs will be posted 24-hours in advance to warn of any scheduled work. Please observe and obey all traffic controls, posted signs, and special duty police officers. Drivers are encouraged to allow extra travel time while driving through the work areas, and to anticipate detours, road closures, and delays.
"Throughout my term, I have been dedicated to improving our aging park facilities and roadways," said Mayor Kirk Caldwell. "This project is a great combination of those two efforts. We hope this project compliments the other improvements that have already been completed at the 'People's Park,' and makes this urban jewel even more inviting for the people of O'ahu."
-PAU-
RECENT IMPROVEMENT PROJECTS COMPLETED
- ʻĀina Moana Shower Improvements: Improved water quality runoff and shower facilities near the comfor station at the base/entrance of Magic Island. It began in December 2018 and was finished by the end of May 2019.
- Park Drive Tree Plantings:Relocation of 14 coconut palm trees from Honolulu Authority for Rapid Transportation (HART) sites on Nimitz Highway to several locations along Ala Moana Park Drive. 28 additional trees are scheduled for planting in late July 2019.
- ʻĀina Moana Storage Room Repairs:Improve structural integrity and electrical capabilities of the staff storage room. Expected to be completed in July 2019.

ʻĀina Moana Exercise Equipment:Installed along the pathways near the lagoon. The project began in July 2018 and ended in August 2018
- ʻĀina Moana (Magic Island) Irrigation Project: Installed a new, smart irrigation system to replace the od patchwork of irrigation lines dating back several decades. Click here for more information.
- Diamond Head Concession Roof Repairs:Replaced the leaking roof installed in 2008. Project began in November 2018 and was finished in February 2019.

Park Trellis Improvements:Replaced the deteriorated frame that was removed for safety reasons in the 1990's. Project began in August 2018 and was finished in the beginning of 2019.
- 'Ewa Bathhouse Improvements:Similar to the improvements to the Diamond Head-end bathhouse (described below), where skylights and security gates installed, roof repaired, ADA-compliance improved, and other interior and exterior repairs. Project began in January 2019 and is expected to be finished by the end of summer 2019. Portable toilets will be provided to the public near the worksite.
-
McCoy Pavilion Auditorium Air Conditioner Replacement:The facilities in McCoy Pavilion will be closed/impacted by a construction project for a new auditorium air conditioning system beginning on July 1, 2019. The project is scheduled to finish the following winter.
Friday, February 8, 2019
2nd Draft Environmental Impact Statement posted
45-day comment period ends March 25, 2019
- Click here (click highlighted text) to view the 2nd Draft Environmental Impact Statement
- To submit testimony or comment, This email address is being protected from spambots. You need JavaScript enabled to view it. (leads to email)
- Click here (click highlighted text) to view the Office of Environmental Quality Control posting of these documents.
The City is proposing to restore, revitalize, enhance, and improve the Ala Moana Regional Park (AMRP) and the Magic Island peninsula grounds and facilities as a result of a recent master plan process that outlined both long-term and short-term improvement plans. The project area receives the most usage of any other park in the State and is also one of the oldest. Many park users visit daily or several times during the week. The City wishes to extend the Parks' longevity as a gradual increase in visits is forecasted for the foreseeable future. Some of the major improvements include sand replenishment, renovations to existing structures, improving pond edges, widening pedestrian access over the drainage canal along Ala Moana Boulevard, create a wider shared use path along Ala Moana Park Drive and reconfiguring the parking. This Second Draft Environmental Impact Statement is being published because additional studies were prepared or updated; these include a new Cultural Impact Assessment, an updated Beach Nourishment report that discusses a new sand source off AMRP, and an update on the Playground.
Monday, July 9, 2018
Revised improvement plans highlighted in Ala Moana Regional Park Draft EIS
45-day comment period begins for improvements projects at "The People's Park"
- Maintaining a majority of the makai parallel parking stalls along the park road (except for the area fronting the reorganized McCoy Pavilion parking lot).
- Reorienting a majority of the mauka parallel parking stalls along the park road to perpendicular parking, thereby adding 94 stalls to this particular parking area.
- Keeping the grass area and plant life along the promenade while upgrading the path to a shared-use capacity, in compliance with the Complete Streets Ordinance and city Rules Relating to Water Quality.
"We are grateful for the passion the public has shown for Ala Moana Regional Park, which has resulted in a better master plan," said Mayor Kirk Caldwell. "Ala Moana is 'The People's Park,' and the proposed improvements will ensure that it continues to thrive for generations to come. I hope more park users take the time to comment on the Draft EIS during the next 45 days."
Other projects highlighted in the Draft EIS include:
- Beach sand replenishment
- Parking lot reconfigurations for McCoy Pavilion and ʻĀinaMoana (Magic Island)
- Renovations to the edges of the drainage canals and two park ponds
- Repairs to the canal bridge and park entrance portals
- Improved pedestrian access near Pi'ikoi and Queen streets
- Adding a dog park and playground
- Renovations to McCoy Pavilion and the Lawn Bowling area
- Improvements to the "high spot and Canoe Hālau area
The above mentioned parking lot reconfigurations, plus the plan for mauka perpendicular stalls, are anticipated to add 216 parking stalls to the state's most popular park facility.
The public can continue to provide input on the proposed improvements; the 45-day public comment period began yesterday, following the publishing of the Draft EIS.
The presentation from the January meeting and a copy of the Draft EIS are available in the "Ala Moana Regional Park" section of the parks.honolulu.gov website.
For more information about how to submit input, due by August 22, 2018, please visit The Environmental Notice publication on the website for the State Office of Environmental Quality Control by clicking here.
The date of publication for the Final EIS will be determined by the extent of the comments received for the Draft EIS. It is expected by early 2019.
Friday, May 25. 2018
Bathhouse renovation project finished, facility reopened to public at Ala Moana Regional Park
Ala Moana – Just in time for Memorial Day weekend, the renovation project for the bathhouse located on the Diamond Head-end of Ala Moana Regional Park is now complete and the facility has been reopened to the public.
This is the facility near the L&L concession by ʻĀina Moana (Magic Island).
The majority of the renovations for this facility were designed to improve security, cleanliness, and usability.
These improvements, which began at the end of 2017, include the following: installation of skylights, reroofing, repairing the tile floor, improving ADA compliance within the restrooms, adding security gates and screens, and replacing the exterior drinking fountains.
Fencing in the open area adjacent to the bathhouse will remain for about a month to allow for the grass to regrow. Surveillance cameras installed on the outside of the bathhouse prior to the renovation project have been reinstalled and reactivated.
Similar improvements to the bathhouse at the Ewa-side of the park are expected to begin in early 2019.
These improvements are the result of the Mayor Kirk Caldwell's 9-Point Community Action Plan calling for immediate improvements to Ala Moana Regional Park.
The $668,000 contract for the bathhouse project was awarded to Amethyst Builder, Inc.
Presentation of the Ala Moana Regional Park Master Plan
"The community has embraced the need to update what President Franklin Delano Roosevelt called 'The People's Park' when it was dedicated back in 1934. I'm pleased this process has generated so many exciting ideas to restore, revitalize and enhance this 119-acre jewel in the heart of urban Honolulu." ~ Mayor Kirk Caldwell
As part of the third installment in a series of public outreach meetings concerning the Master Plan for Ala Moana Regional Park, held on January 29, 2018, a presentation was delivered concerning the accomplished goals and current plans for long and short term improvements to "The People's Park." These improvements were drafted as a result of the two prior public forums in March 2015 and April 2016. During those forums, the public shared their vision of the park's future and how they would like to see the park improved, all while maintaining the park's current character. The public was also invited to provide feedback online at www.ouralamoanapark.com. Following the third public meeting in 2018 meeting, this website will be the best location for information about the Master Plan.
Prior to the presentation, the public was and is still encouraged to view the Environmental Impact Statement Preparation Notice (EISPN, click the previous text for a PDF copy), now available online. The draft Environmental Impact Statement is expected to be completed by the end of summer 2018. Additional comment periods are allowed during the EIS process. Those dates will be publicized once they are finalized.
CLICK HERE FOR A COPY OF THE JANUARY 2018 PRESENTATION
Below is a summary of the information provided during the presentation.
While this Master Plan was being drafted, more immediate park improvements have been implemented through the Mayor's 9-Point Community Action Plan, all of which have been or are currently being addressed.
- Hire park staff:
- 14 permanent staff hired including groundskeepers and park caretakers
- Renovate comfort stations:
- Current improvements to Diamond Head Bathhouse and future renovations to Ewa Bathhouse
- Improvements to the ʻĀina Moana comfort stations
- Future outdoor shower improvements at ʻĀina Moana
- Repair ʻĀina Moana (Magic Island) exercise path and exercise ammenities:
- ʻĀina Moana pathway repaved, sealed, and painted
- Completion of the island's first designated sand volleyball courts
- Additional exercise equipment cluster to be installed
- Tennis court resurfacing
- Irrigate Great Lawn:
- Completion of the new central-controlled irrigation system for the main 76-acre body of the park set for summer 2018
- ʻĀina Moana irrigation improvements scheduled to begin March 2018
- Fix rocky beach areas:
- Staff and volunteer efforts to relocate rocks along shoreline October 2016
- Sand pushing and cleaning efforts
- Beautify the park:
- Planted 42 trees along Ala Moana Boulevard in Fall 2016
- Installed new hooded steel trash receptacles through a private-public partnership in September 2017
- PSA on dangers of improperly dumping coals
- Build a new playground:
- On-going process through a public-private partnership
- Make the park safer:
- Security cameras installed at the two bathhouse facilities. No vandalism reported at those sites following the first year of operation.
- All existing lights at bathhouses, comfort stations, and concessions upgraded to brighter, energy-efficient LED lighting. Additional conversions planned
- Additional park rangers monitoring park during afternoon hours
- Security gates and screens added to comfort stations
- Local favorites in the concession:
- Two L & L BBQ locations opened beginning summer 2015.
- Activate Wi-Fi access at these locations
- Reroofing of Diamond Head concession
Ala Moana Regional Park as we know it today rests on reclaimed land that was once swampy marshland. It was part of historic change in land-use, a large development of open areas needed for additional space beginning in the 1920's.
Structural construction of the park began soon after the land was created in the 1930's. A Sport Pavilion, Banyan Court, lawn bowling green, Bridle Path Bridge, and the Roosevelt entry Portals were some of the initial park ammenities. The two ponds and drainage canals were additionally dredged around 1932 for both aesthetic and the practical purpose of control local water run-off. The park was dedicated in 1934 by then president Franklin Delano Roosevelt and dubbed "The People's Park".
Following the use of the park as a military battery and staging area during WW II, the park experienced restoration and evolution throughout the 1990's. Beginning in 1954, the mile-long sandy beach fronting the park was constructed. Today that beach requires periodic sand replenishment due to erosion. Nourishing the beach is an element of the Master Plan. From 1957 to 1961 several park features were added, including concession and bathhouse facilities at both the Diamond Head and Ewa ends of the park. In 1962, the 47-acre ʻĀina Moana (Magic Island) was constructed. Originally conceptualized as a major resort area, it was later added to the park as additional open space. 1975 saw the addition of McCoy Pavilion and later in the 1990's additional bridges were added over the canals.
In 1988, the park was added to the State Register of Historic Places. Preservation and restoration of these structures is a key element of the current Master Plan.
Today, the significance of the park remains paramount in the lives of local residents and visitors. As one of the state's oldest and busiest parks, currently seeing an estimated four million users every year, Ala Moana Regional Park has become an integral part of our island community. The city hopes this facility will continue to be a resource that the public treasures, all while hosting annual events, such as the Lantern Floating Hawaiʻi ceremony and Independence Day fireworks, and special occasions, such as the return of the Hōkūleʻa.
The purpose of the EISPN for the Master Plan is to outline a variety of short and long-term projects and park improvements to restore, revitalize, and enhance Ala Moana Regional Park, including ʻĀina Moana (Magic Island). Proposed actions include:
- Sand replenishment and long-term beach nourishment
- Mitigate stresses to the beach including: erosion, sea level rise, King Tides, no natural source of sand
- Raise elevation and widen beach
- Reconfiguring parking layout without losing stalls and improving the roadway
- Increase the total number of stalls in the park. Currently 950 stalls exist within the park
- Removing parallel parking along Ala Moana Park Drive and adding perpendicular parking along the mauka side of the road. Additional plans for loading and unloading zones.
- Two-way traffic flow remaining
- McCoy Pavilion Keyhole parking lot expansion/redesign
- Elongating ʻĀina Moana parking lot
- Repaving Ala Moana Park Drive
- Renovating McCoy Pavilion and the Banyan Courtyard
- Renovating and ehancing the entryways
- Additional seating and greenery ourtside of the facility
- Air condition replacement
- Added pathways and activation of the Diamond Head side
- Preserve historic structures
- Enhancing entrances into the park
- Widening pedestrian access at Pi'ikoi and Queen streets
- Covering drainage canals for easier access
- Repairing the historic walls and structures at Kamake'e and Atkinson entrances
- Widening sidewalks at the vehicular entrances
- Expansion of promenades along Ala Moana Park Drive and the Ala Wai Boat Harbor
- Provide more seating, shade trees, and greenery
- Wider path for pedestrians and bicycles
- Improvements to the canoe launch ramp and crosswalk
- Improving to the central raised area
- Repairing and enhancing the terrace
- Redesign for additional access
- Improving the edges of waterways
- Hardscaping and enhancing pond edges
- Drainage canal coverings
- Incorporating a multi-use facility into the Lawn Bowling area
Source: https://www.honolulu.gov/parks/default/park-locations/182-site-dpr-cat/30221-ala-moana-regional-park.html
0 Response to "Moana Tent Moana Bedroom Decor"
Post a Comment